A project team is leading a software development project.

A project team is leading a software development project. During the project kickoff meeting, the risk manager discovers that a vendor has not finalized the timeline for delivering an essential component. This creates uncertainty in the overall project schedule.

What should the risk manager do to address the risk?

A.

Hold a meeting to assess the risk's impact and create a response plan with alternative timelines.

B.

Adjust the overall project schedule based on assumptions about the vendor's timeline.

C.

Defer the risk discussion until the vendor finalizes the timeline to prioritize the project's start.

D.

Focus on internal risks and assume the vendor will resolve the issue independently.

PMI PMI-RMP Summary

  • Vendor: PMI
  • Product: PMI-RMP
  • Update on: Jul 25, 2025
  • Questions: 264
Price: $52.5  $149.99
Buy Now PMI-RMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method