Summer Special Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: vce65

During a risk identification process in a construction project, the lack of space to install...

During a risk identification process in a construction project, the lack of space to install air conditioners is raised as a risk with high impact. Which is an example of an early risk trigger?

A.

A potential need to share the space with other machinery

B.

A different type of equipment received before installation

C.

A time delay during air conditioning installation activities

D.

A quality nonconformance issue raised during the inspection

PMI PMI-RMP Summary

  • Vendor: PMI
  • Product: PMI-RMP
  • Update on: Oct 17, 2025
  • Questions: 264
Price: $52.5  $149.99
Buy Now PMI-RMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method