Comprehensive and Detailed In-Depth Explanation:
When there is confusion among stakeholders regarding agile concepts, the best course of action is to provide training to ensure all stakeholders have a common understanding of agile principles and terminology.
Option A: Organize training sessions to create awareness around the agile values for stakeholders (Correct Answer).
Training sessions help bridge knowledge gaps by ensuring that stakeholders understand agile principles, frameworks (Scrum, Kanban, XP), and terminology.
The PMI-RMP Guide highlights that effective stakeholder engagement requires education and alignment on risk management strategies, which applies here as well (PMI Risk Management in Portfolios, Programs, and Projects – A Practice Guide, 2022, p. 78).
Educating stakeholders reduces resistance to change and promotes informed decision-making.
PMI’s Agile Practice Guide emphasizes that “a shared understanding of agile principles across all levels of an organization increases agility and reduces friction during decision-making” (PMI & Agile Alliance, 2017, p. 44).
Option B: Facilitate a face-to-face discussion and have stakeholders agree to shift to agile for future projects (Incorrect).
Forcing a decision before stakeholders fully understand agile methodologies could lead to resistance and ineffective implementation.
The decision should be based on business needs rather than prematurely committing to agile.
Option C: Recommend an external facilitator as no one in the organization is able to eliminate this roadblock (Incorrect).
While an external facilitator can help in some situations, the Scrum Master is already responsible for coaching the organization on Scrum and Agile methodologies (Scrum Guide, 2020).
The Scrum Master should take the lead in educating stakeholders before escalating the issue externally.
Option D: Allow stakeholders to discuss without the Scrum Master’s intervention (Incorrect).
Without proper guidance, discussions could lead to further misinterpretations and delays.
The Scrum Master is responsible for educating and guiding stakeholders in understanding agile (Scrum Guide, 2020).
Final Verdict:
The correct answer is A (Organize training sessions to create awareness around agile values for stakeholders) because training ensures a common understanding, reduces resistance, and promotes effective decision-making.
[References:, PMI. Agile Practice Guide (2017). PMI & Agile Alliance., PMI. Risk Management in Portfolios, Programs, and Projects – A Practice Guide (2022)., Scrum.org. The Scrum Guide (2020)., , , ]