While executing an oil extraction project in an environmentally sensitive area, weather is the main...

While executing an oil extraction project in an environmentally sensitive area, weather is the main cause of delay in the project work. The risk manager was aware that the delays caused by the weather could not be avoided or mitigated.

What should the risk manager do to manage this risk?

A.

Perform time recovery actions.

B.

Execute the prevention plans.

C.

Execute the contingency plans.

D.

Perform change management.

PMI PMI-RMP Summary

  • Vendor: PMI
  • Product: PMI-RMP
  • Update on: Jul 25, 2025
  • Questions: 264
Price: $52.5  $149.99
Buy Now PMI-RMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method