PMI PMI-SP Question Answer
Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the cost variance for this project that Fred needs to report to management?
PMI PMI-SP Summary
- Vendor: PMI
- Product: PMI-SP
- Update on: Jul 25, 2025
- Questions: 323