PMI PMI-SP Question Answer
George is the project manager of the NHQ Project and has a budget of $778,000. The project is scheduled to last for one year with an equal amount of work completed each quarter. The second quarter of the project has ended and George has spent $325,000 but has only finished forty percent of the project. Management needs a variance report for the project schedule. What value should George report in this instance?
PMI PMI-SP Summary
- Vendor: PMI
- Product: PMI-SP
- Update on: Jul 25, 2025
- Questions: 323