Harry works as a project manager for BlueWell Inc.

Harry works as a project manager for BlueWell Inc. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. Who among the following is responsible for implementing the risk responses or contingency plan?

A.

Risk owner

B.

Harry

C.

Project sponsor

D.

Subject matter expert