Summer Sale Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 45285der6

John is the project manager for the ABC project.

John is the project manager for the ABC project. He is finalizing the budget of the project. He is concerned about the direct costs involved in the project. Which of the following can be considered a direct cost in the project?

A.

Cost of electrical utilities

B.

Salaries of management directly involved in the project

C.

Subcontract cost

D.

Accounting support cost

PMI PMI-SP Summary

  • Vendor: PMI
  • Product: PMI-SP
  • Update on: Sep 15, 2025
  • Questions: 323
Price: $52.5  $149.99
Buy Now PMI-SP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method