John is the project manager for the ABC project.

John is the project manager for the ABC project. He is finalizing the budget of the project. He is concerned about the direct costs involved in the project. Which of the following can be considered a direct cost in the project?

A.

Cost of electrical utilities

B.

Salaries of management directly involved in the project

C.

Subcontract cost

D.

Accounting support cost