John works as a project manager for BlueWell Inc.

John works as a project manager for BlueWell Inc. His project has a budget of $795,000 and he has spent $325,000 on the project. But, he has completed only 40 percent of the project work till now. Management wants to know what the project's cost performance index is. What value will John report?

A.

0.76

B.

0.85

C.

0.80

D.

0.92