Lily works as a project manager for BlueWell Inc.

Lily works as a project manager for BlueWell Inc. She has recorded the following duration estimates for an activity in her project: optimistic 35, most likely 50, and pessimistic 95. What time will she record for this activity?

A.

48

B.

55

C.

54

D.

40