Tom is the project manager of the HQQ Project.

Tom is the project manager of the HQQ Project. His project has a schedule variance of -$34,500 due to some errors early in the project. Management would like to know how Tom will respond to these variances. What action can help Tom to manage the errors in the project and to ensure that the errors would not occur again?

A.

Lesson learned documentation

B.

Risk analysis

C.

Preventive action

D.

Corrective action