You are the project manager of a project that has a budget of $675,000 and...

You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?

A.

-$135,000

B.

.67

C.

.81

D.

-$65,000

PMI PMI-SP Summary

  • Vendor: PMI
  • Product: PMI-SP
  • Update on: Jul 25, 2025
  • Questions: 323
Price: $52.5  $149.99
Buy Now PMI-SP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method