You are the project manager of the NHQ Project.

You are the project manager of the NHQ Project. This project has a Budget at Completion of $750,000 and is expected to take 18 months to complete. The project is supposed to be 75 percent complete, but due to some errors the project is only 60 percent complete. At this time the project has spent $465,500. Management has asked you to review the project work and report the project's SPI. What is the SPI for this project?

A.

0.97

B.

0.80

C.

$562,500

D.

-$112,500

PMI PMI-SP Summary

  • Vendor: PMI
  • Product: PMI-SP
  • Update on: Jul 25, 2025
  • Questions: 323
Price: $52.5  $149.99
Buy Now PMI-SP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method