You are working with your project team to control the project schedule.

You are working with your project team to control the project schedule. You will need five inputs to this process throughout your project. Which one of the following is an output of the project schedule control, and NOT an input?

A.

Work performance information

B.

Project schedule

C.

Project management plan

D.

Work performance measurements