You have a project to install 45,900 emergency exit signs throughout a university campus.

You have a project to install 45,900 emergency exit signs throughout a university campus. You have a crew of 45 project team members to install the signs and they are making good progress on the installation but it looks like they'll miss the promised end date. Your project requires all of the signs to be installed one week before classes are scheduled to begin. You elect to crash the project in an effort to shorten the installation duration activity. What does it mean to crash the project?

A.

Increase the working hours.

B.

Level the project schedule.

C.

Add more workers.

D.

Reduce the project scope.

PMI PMI-SP Summary

  • Vendor: PMI
  • Product: PMI-SP
  • Update on: Jul 25, 2025
  • Questions: 323
Price: $52.5  $149.99
Buy Now PMI-SP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method