You work as a project manager for BlueWell Inc.

You work as a project manager for BlueWell Inc. You are creating the activity list for the project. The activity list is based on the work packages defined in the project's WBS. Activities provide a basis for all of the following information except for which one?

A.

Scope baseline

B.

Executing

C.

Scheduling

D.

Estimates