A city infrastructure project aims to construct a bridge to enhance traffic flow and alleviate...

A city infrastructure project aims to construct a bridge to enhance traffic flow and alleviate congestion. The project is under tight deadlines due to upcoming major events in the city. The team is employing a hybrid approach by incorporating agile practices into a traditionally structured project schedule.

A key stakeholder asks the project manager to expedite the delivery of specific work packages. The project manager determines that this request will affect the project cost.

What should the project manager do?

A.

Continue with the project as planned because the stakeholder lacks the authority to request a change.

B.

Escalate the problem to the project sponsor and request additional funds to ensure early completion.

C.

Advise the stakeholder to follow the change control board (CCB) process and to submit a change request.

D.

Inform the requester that change is infeasible and unnecessary and it will impact the entire project.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 2, 2026
  • Questions: 187
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method