A company is going through a large cost-cutting initiative.

A company is going through a large cost-cutting initiative. Senior management requests a report on the work remaining for outstanding projects.

Which tool should the project manager use for this purpose?

A.

Cumulative flow diagram

B.

Earned value (EV)

C.

Burndown chart

D.

Forecast estimation