PMI PMP Question Answer
A company is running a project to eliminate a sales channel that has been unprofitable for the past 3 years. A key stakeholder from another area, who has legacy ties to that sales channel, objects to the project.
What should the project manager do in this situation?
PMI PMP Summary
- Vendor: PMI
- Product: PMP
- Update on: Dec 5, 2025
- Questions: 2040