A construction project is in its final stage when the owner of a private property...

A construction project is in its final stage when the owner of a private property where the pipeline is routed refuses to collaborate. The lack of collaboration causes a project delay, but the client insists that the project must be completed as per the contract. What should the project manager do next?

A.

Request additional budget from the project sponsor and raise a dispute with the property owner to force them to collaborate.

B.

Use the contingency reserve, add more resources, and reroute the pipeline to complete the project as per the contract timeline.

C.

Escalate the routing pipeline issue to the project change control board (CCB) and wait for a resolution to the conflict.

D.

Review the agreement with the property owner, schedule a meeting with them to discuss their concerns, and inform the client.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Mar 19, 2026
  • Questions: 2134
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method