PMI PMP Question Answer
A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.
In which project document should the project manager record the concern?
PMI PMP Summary
- Vendor: PMI
- Product: PMP
- Update on: Jul 29, 2025
- Questions: 1877