A construction project to build a fish hatchery is in execution.

A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.

In which project document should the project manager record the concern?

A.

Request for information

B.

Scope statement

C.

Issue log

D.

Risk register