A global petroleum crisis has affected the distribution of crude oil in the region where...

A global petroleum crisis has affected the distribution of crude oil in the region where the construction project is underway Materials are not being delivered on time and this phase of construction is already behind for what was initially planned.

What should the project manager do first to prevent the project from going further off track?

A.

Perform a risk assessment and define a risk response action plan.

B.

Proceed with the project using management reserves to cover any delays or losses.

C.

Propose a pause in this phase to save labor costs and asset depreciation.

D.

Establish new partnerships with other suppliers in anticipation of any delays.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method