A key customer stakeholder asks the project team to include new tasks in the backlog...

A key customer stakeholder asks the project team to include new tasks in the backlog and begin analyzing new requests. The customer expects results as soon as possible and pressures the team to attend noncritical meetings. The team is frustrated by this situation.

How should the project manager approach this situation?

A.

Understand the customer's perspective and provide mentoring on agile mindsets.

B.

Call for an internal team retrospective and create an improvement action plan.

C.

Ask the customer to work with the product owner to prioritize all requests.

D.

Work with the team to receive customer directions and improve the process.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method