PMI PMP Question Answer
A key project stakeholder showed interest in the beginning of a complex agile project but has become less involved as the sprint has progressed due to additional responsibilities A few sprints later, the key stakeholder rejected a feature deliverable The team is reworking the rejected deliverable for the next sprint
What should the project manager have done to avoid this situation?