A member of a testing team in an agile project works well with the project...

A member of a testing team in an agile project works well with the project team. However, in the previous two iterations, this team member's performance was poor, and the team had difficulty meeting the iteration goals.

How should the project manager handle this situation?

A.

Inform the human resource (HR) department about the issue.

B.

Allow the project team to discuss the problem with this team member.

C.

Discuss the issue with the team member's functional manager.

D.

Speak to the team member regarding the need to improve performance.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Mar 19, 2026
  • Questions: 2134
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method