A new major project is starting that consists of two interconnected subprojects.

A new major project is starting that consists of two interconnected subprojects. One of the subprojects was assigned to a contractor who commits to submitting biweekly status reports and attending weekly integration meetings. Halfway through the project, the contractor stops participating in the meetings and does not submit the reports. Their excuse is that these activities are consuming too much time.

How should the project manager handle this situation?

A.

Remind the contractor to join the meetings and submit their report as this is their commitment.

B.

File a claim for not fulfilling the contract terms in accordance with alternative dispute resolution.

C.

Compromise with the contractor to only attend the weekly meetings without submitting the reports.

D.

Assess the situation as a risk and reach out to the contractor to check the origin of this resistance.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 2, 2026
  • Questions: 187
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method