PMI PMP Question Answer
A new manufacturing line project is planned to be delivered in iterations tor the equipment installation phase. During one of the iterations the vendor communicates to the project manager that they will not be able to deliver some of the equipment at the agreed dates.
What should the project manager do next?
PMI PMP Summary
- Vendor: PMI
- Product: PMP
- Update on: Aug 13, 2025
- Questions: 1988