A new project team has formed and the project manager notices that some of the...

A new project team has formed and the project manager notices that some of the team members do not feel comfortable being part of the project team As a result members of the team are working individually and not as a team

What should the project manager do to resolve this?

A.

Facilitate a team-building meeting to help this issue

B.

Allow the team members to remain in their former individual roles

C.

Directly guide the team members on how to perform their tasks

D.

Wait until some iterations are completed to intervene

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method