A new regulation has been approved that will impact the deliverables in the fourth phase...

A new regulation has been approved that will impact the deliverables in the fourth phase of the project The delivery is following an iterative approach and is currently completing the second phase.

What should the project manager do next?

A.

Consult with the project sponsor to discuss a cost increase

B.

Acquire approval for an exception to the implementation of the new regulation.

C.

Get approval for the additional budget from the steering committee

D.

Meet with subject matter experts (SMEs) to assess the impact to objectives

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method