A new relevant project stakeholder suggested a change to some of the project parameters midway...

A new relevant project stakeholder suggested a change to some of the project parameters midway through execution What should the project manager do next?

A.

Accept the change and use contingency funds to implement this change with minimal schedule impacts

B.

Reject the change because it is contrary to what was agreed to during earlier phases of the project

C.

Transfer the change to the steering committee for them to evaluate and decide the appropriate next steps

D.

Evaluate the proposed change with integrated change controls and discuss the change with the project sponsor

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Jul 29, 2025
  • Questions: 1877
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method