Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmasmnth

A newly assigned team member immediately begins questioning operating procedures.

A newly assigned team member immediately begins questioning operating procedures. This new team member wants the team to follow operating procedures that the team member had used previously. During assignments, the new team member begins using some of those processes and procedures and suggests these practices to other team members.

What action should the project manager take?

A.

Organize a training for the new team member on the processes the team is currently using.

B.

Speak with the new team member at the retrospective and discuss potential improvements.

C.

Formalize the new processes and implement the team member's proposed changes.

D.

Hold a team meeting on governance, operating policies, procedures, and practices.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Oct 19, 2025
  • Questions: 594
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method