PMI PMP Question Answer
A newly hired team member just joined the project team and reports directly to the
project manager. In the first week, this new member tells the project manager that there is a
task priority conflict with hard, dependent tasks on the critical path.
What should the project manager do to handle the conflict?
PMI PMP Summary
- Vendor: PMI
- Product: PMP
- Update on: Dec 5, 2025
- Questions: 2040

