A newly hired team member just joined the project team and reports directly to theproject...

A newly hired team member just joined the project team and reports directly to the

project manager. In the first week, this new member tells the project manager that there is a

task priority conflict with hard, dependent tasks on the critical path.

What should the project manager do to handle the conflict?

A.

Guide the team member on how to resolve the conflict.

B.

Analyze the project schedule and look for alternatives.

C.

Perform crashing and/or fast tracking of the schedule.

D.

Meet the team member and try to plan a course of action together.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Dec 5, 2025
  • Questions: 2040
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method