A project engineer in country A is complaining about the sample received from the supplier...

A project engineer in country A is complaining about the sample received from the supplier in country B because the sample is not the correct length. During a telephone conference, the supplier checked the drawings and insisted that the measurement was accurate.

What should the project manager do next?

A.

Escalate the issue to the purchasing department for review.

B.

Evaluate the procurement contract to determine the agreed-upon specifications.

C.

Hire a company in country B to perform a quality check before shipment.

D.

Add an additional task to cut the received part according to the specifications,

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method