A project has a schedule performance index (SPI) of 0.

A project has a schedule performance index (SPI) of 0.75 and a cost performance index (CPI) of 1.1. As a result, the project manager is considering either fast-tracking or crashing the project schedule to bring the project back on track again. What could be a secondary result of these actions?

A.

A decrease in the project cost

B.

An increase in the project risk

C.

Additional project scope

D.

Additional resources