A project has been reporting a declining schedule performance index (SPI) for the past four...

A project has been reporting a declining schedule performance index (SPI) for the past four reviews. No corrective action is under development, and the project team does not seem concerned.

What should the project manager do first to address the SPI trend?

A.

Notify the project stakeholders that the scope needs to be reduced in order to hold the costs within budget.

B.

Engage with the project team to create a plan that will deliver benefits on a defined and incremental basis.

C.

Contact the project sponsor to let them know you require more resources to meet the schedule.

D.

Meet with the project scheduler to rebaseline the project using a more realistic schedule.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 2, 2026
  • Questions: 187
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method