A project has met the agreed-upon product requirements and is closing.

A project has met the agreed-upon product requirements and is closing. There is time remaining in the schedule and excess budget. The

resources are not yet scheduled to move to other projects. Several product champions want to continue adding functionality to the product.

What should the project manager do?

A.

Use the remaining time and resources to add additional scope to the project without spending the project budget.

B.

Ensure product quality by spending the remaining resources and time on additional quality checks for the product.

C.

Acknowledge the project closure criteria has been met and release the remaining budget and resources.

D.

Obtain approval from the sponsor to add additional functionality to the project deliverables with the leftover budget.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method