A project has obtained all of the necessary legal requirements and policies from the local...

A project has obtained all of the necessary legal requirements and policies from the local government. During the execution phase, the product owner is informed that a new law impacting the project deliverables will be published within two weeks.

What should the project lead do?

A.

Review the product backlog items to evaluate the impact on scope and prioritize accordingly.

B.

Develop a change request for more resources and update the project budget and schedule.

C.

Ask the internal legal department to evaluate if the regulatory law could be managed internally.

D.

Work with the team to develop an alternative solution with no additional effect on the project's budget.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Oct 19, 2025
  • Questions: 594
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method