PMI PMP Question Answer
A project is ending its fifth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration.
What should the project lead do?
PMI PMP Summary
- Vendor: PMI
- Product: PMP
- Update on: Aug 13, 2025
- Questions: 1988