A project is late due to a large number of scope changes.

A project is late due to a large number of scope changes. This was raised as a risk in the risk register during the initiation phase. The team is afraid that they will be blamed in case of failure and recommends that the project manager ask for an extension.

What should the project manager do first?

A.

Ask the sponsor for their advice on the way forward.

B.

Ask the team to document the impact of the risk in detail.

C.

Refer to the risk register and follow the mitigation plan.

D.

Refer to the change log and ensure that changes are documented.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Oct 19, 2025
  • Questions: 594
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method