A project is on its fifth iteration out of six.

A project is on its fifth iteration out of six. One member of the team has left the company unexpectedly.

What should the project manager do next?

A.

Detail the reason for the project delay in the status report.

B.

Invite the stakeholders to discuss a mitigation plan.

C.

Take on some of the necessary work to minimize the impact.

D.

Register an issue and escalate it to the project sponsor.