A project is on schedule.

A project is on schedule. However, during a site visit, a project manager notices that the contractor's productivity is low.

What should the project manager do?

A.

Assess the opportunity to deliver the project ahead of schedule and introduce a reward system.

B.

Discuss the need to increase productivity with the contractor.

C.

Plan the close-out activities since the project is on schedule.

D.

Update the project schedule to align with the contractor's productivity.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Mar 19, 2026
  • Questions: 2134
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method