A project is successfully delivering its product outcomes, and the customer satisfaction rating is high.

A project is successfully delivering its product outcomes, and the customer satisfaction rating is high. However, during an internal audit, it is discovered that certain essential process documents and approvals are missing, and the project is evaluated as being noncompliant.

What should the project manager do next?

A.

Review the latest project management standards with the project management office (PMO) and make changes to the quality management plan.

B.

Perform quality assurance to review the processes against the quality management plan and identify gaps.

C.

Review and update the project document repository with the missing documents and approvals.

D.

Change the quality management processes to align with the project objective.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method