A project lead was recently elected to complete the execution of a legacy project for...

A project lead was recently elected to complete the execution of a legacy project for a water filtration plant due to the project director's reassignment. The project lead has been on five similar projects in the recent past. The client has challenged the completion status due to a lack of construction evidence. The client has also indicated their intention to apply performance-associated penalties that are detailed in the contract.

What should the project lead do?

A.

Accept the client's observations and pay the penalties as per the project contract details.

B.

Investigate the client's project reports and proceed to negotiate the levying of any penalties.

C.

Inform the project director of the change and complete the project so as to not incur any penalties.

D.

Request for the recall of the project director to investigate the situation and negotiate potential penalties.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method