A project learn member identified a defect in the initial solution design for a project...

A project learn member identified a defect in the initial solution design for a project The stakeholders are not sure whether to deploy the system or not. What should the project manager do?

A.

Propose a solution redesign for the project

B.

Perform risk analysis against the issue.

C.

Revise the project's quality control measurements

D.

Develop a mitigation based on the solution design