A project manager finished reviewing the project deliverables for the current iteration with the customer...

A project manager finished reviewing the project deliverables for the current iteration with the customer A new key stakeholder who just joined the customer's team, complains that the results do not provide the capabilities the business anticipated

What should the project manager do to address this issue?

A.

Create a change request and update the scope management plan

B.

Conduct stakeholder identification and a project objectives review session

C.

Update the stakeholder list and fix the deliverables

D.

Update the project management plan and lessons learned

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method