A project manager has been assigned to a new project.

A project manager has been assigned to a new project. The project sponsor has requested a detailed timeline, but the project includes some deliverables that are not yet clearly defined.

Which project management approach should the project manager advise using?

A.

As the project includes elements that are not yet clearly defined, an agile approach is the best option.

B.

As the project sponsor has requested a detailed timeline up front, an agile approach is the best option.

C.

As the project appears to have both agile and predictive elements, a hybrid approach is the best option.

D.

As the project includes elements that are not yet clearly defined, a predictive approach is the best option.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Dec 5, 2025
  • Questions: 2040
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method