PMI PMP Question Answer
A project manager has been assigned to a new project that is similar to a project that was closed last year. There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule.
What should the project manager do?
PMI PMP Summary
- Vendor: PMI
- Product: PMP
- Update on: Dec 5, 2025
- Questions: 2040

