Cyber Monday Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmasmnth

A project manager has received an updated earned value analysis report The following are the...

A project manager has received an updated earned value analysis report The following are the key findings from the report

•Budget at completion = USS1 million

•Earned value = US$0 7 million

•Actual cost = US$0 75 million

•Cost performance index = 0 933

Based on this information, what should the project manager conclude about project performance'?

A.

The project will be completed exactly as planned

B.

The project will be easier to complete than planned

C.

The project will be difficult to complete as planned.

D.

The project will not be completed as planned

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Dec 5, 2025
  • Questions: 2040
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method