A project manager has recently been assigned to a construction project.

A project manager has recently been assigned to a construction project. The project has hundreds of stakeholders and three stages. The project manager recognizes that many steps have already been started, including risk identification. The project sponsor asks the project manager to rank the risks contained in the register. How should the project manager respond to the request?

A.

Execute a qualitative analysis to provide identified risks prioritization.

B.

Inform that a quantitative risk prioritization was completed using Monte Carlo simulation.

C.

Inform that a qualitative analysis has already been completed.

D.

Perform a quantitative analysis to provide identified risks prioritization.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Mar 19, 2026
  • Questions: 2134
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method