A project manager is asked to manage an agile project, allowing the company to comply...

A project manager is asked to manage an agile project, allowing the company to comply with a new upcoming regulation. After the project kickoff, the scope is modified to have the project team work on specific tasks, while a global team will manage the program for several countries in parallel. The project management plan has not yet been shared, and the deadline to complete the project is fixed.

What should the project manager do to handle the scope change?

A.

Define an initial backlog and start working on the clearest tasks, then incrementally refine the scope.

B.

Create a risk entry in the risk management plan due to the lack of a global project management plan.

C.

Review the organizational process assets (OPAs) from past projects with similar scope changes.

D.

Formalize the change in the scope with the project sponsor to limit accountability for the specific tasks.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Oct 19, 2025
  • Questions: 594
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method